SECTION 03540
SELF-LEVELING CONCRETE FLOOR UNDERLAYMENT
RECOMMENDED SPECIFICATION FOR LEVEL-RIGHT® CEMENTITIOUS SELF-LEVELING FLOOR
UNDERLAYMENT
PART 1 GENERAL
1.01 SUMMARY
A. This is the recommended specification for Level-Right Cementitious Self-Leveling
Floor Underlayment.
1.02 SECTION INCLUDES
A. Level-Right Cementitious Self-Leveling Floor Underlayment
B. Maxxon Floor Primer
C. Maxxon Overspray
1.03 QUALITY ASSURANCE
A. Installer's Qualifications: Installation of Level-Right shall be by an applicator
authorized by the Maxxon Corporation using Maxxon approved mixing and pumping
equipment.
1.04 DELIVERY, STORAGE AND HANDLING
A. General Requirements: Materials shall be delivered in their original, unopened
packages, and protected from exposure to the elements. Damaged or deteriorated
materials shall be removed from the premises.
1.05 SITE CONDITIONS
A. Environmental Requirements: Before, during and after installation of Level-Right,
building interior shall be enclosed and maintained at a temperature above 40
degrees F (4.4 degrees C) and below 100 degrees F (37.7 degrees C) until structure
and subfloor temperature are stabilized.
PART 2 PRODUCTS
2.01 MATERIALS
A. Cementitious Self-Leveling Poured Floor Underlayment: Floor underlayment
compound shall be Level-Right Self-Leveling Floor Underlayment as manufactured
by Maxxon Corporation, Hamel, MN.
B. Sand Aggregate: Sand shall be silica aggregate meeting requirements of Level-Right
Sand Specification 101.
C. Mix Water: Potable, free from impurities.
D. Subfloor Primer: Maxxon Floor Primer
E. Sealer: Maxxon Overspray
2.02 MIX DESIGNS
A. General Requirements: Level-Right mix proportions and methods shall be in
strict accordance with product manufacturer recommendations.
PART 3 EXECUTION
3.01 PREPARATION
A. Condition and Cleaning of Subfloor: Subfloor shall be structurally sound.
General Contractor shall clean subfloor to remove mud, oil, grease, and other
contaminating factors before arrival of the Level-Right underlayment crew.
B. Leak Prevention: Fill cracks and voids with a quick setting patching or caulking
material where leakage of Level-Right could occur.
C. Priming Subfloor: Prime concrete subfloor using the Maxxon Floor Primer.
Priming instructions vary according to the porosity of the concrete, multiple
coats may be necessary.
D. Expansion Joints: Allow joints to continue through the Level-Right at the
same width.
3.02 APPLICATION OF SELF-LEVELING FLOORING
A. Scheduling: Application of Level-Right shall not begin until the building
is enclosed, including roof, windows, doors, and other fenestration. Install
after drywall installation unless tenant finish requirements identify partitioning
after the pour.
B. Application: Place Level-Right from 3" (76 mm) to featheredge. Spread
and float Level-Right to a smooth surface. Except at authorized joints, place
Level-Right as continuously as possible until application is complete so that
no Level-Right slurry is placed against Level-Right product that has obtained
its initial set.
C. Drying: General Contractor shall provide continuous ventilation and adequate
heat. With Level-Right there's no extensive curing time. Ceramic tile can be
thin set within 2 to 4 hours. Other floor goods can be installed once Level-Right
passes a moisture test.
3.03 PREPARATION FOR INSTALLATION OF GLUE DOWN FLOOR GOODS
A. Sealing: Seal all areas that receive glue down floor goods according to the
Maxxon Corporation's specifications. Any floor areas where the surface has been
damaged shall be cleaned and sealed regardless of floor covering to be used.
Use Maxxon Overspray to seal the Level-Right prior to installation of glue down
floor goods. Where floor goods manufacturers require special adhesive or installation
systems, their requirements supersede these recommendations.
B. Floor Goods Procedures: See the Maxxon Corporation's "Procedures for
Attaching Finished Floor Goods to Maxxon Underlayments" brochure for guidelines
for installing finished floor goods. This procedure is not a warranty and is
to be used as a guideline only.
3.04 FIELD QUALITY CONTROL
A. Slump Test: Level-Right mix shall be tested for slump as it's being pumped
using a 2 inch by 4 inch (50 mm by 101 mm) cylinder resulting in a patty size
of 9-1/2 inches (241 mm) plus or minus 1 inch (25 mm) diameter.
B. Field Samples: At least one set of 3 molded cube samples shall be taken from
each day's pour during the Level-Right application. Cubes shall be tested as
recommended by the Maxxon Corporation in accordance with modified ASTM C 109.
Test results shall be available to architect and/or contractor upon request
from applicator.
3.05 PROTECTION
A. Protection From Heavy Loads: During construction, place temporary wood planking
over Level-Right wherever it will be subject to heavy wheeled or concentrated
loads.
END OF SECTION
*****